13. Taida Construction Co. has consistently used the percentage-of-completion method of recognizing revenue. During 2018,
Taida entered into a fixed-price contract to construct an office building for $28,000,000. Information relating to the
contract is as follows:
(A) $6,720,000
(B) $6,930,000
(C)$7,350,000
(D) $10,080,000