41. How much time should be spent performing a feasibility study?
(A)only as long as needed to determine feasibility in broad terms
(B)as much time as management will allow since that is the only way to prevent project failure
(C)as much time as possible to save time in the later stages of project development
(D)feasibility studies typically comprise at least half of the total time required for a project

答案:登入後查看
統計: A(3), B(2), C(4), D(1), E(0) #2957693