17.一專案因顧客需求不斷改變,也未有相對應的變更控制流程,最後使得該專案做不下去。請問該專
案遇到何種問題?
(A)範疇潛變(scope creep)
(B)鍍金(gold plating)
(C)衍生風險(secondary risks)
(D)殘留風險(residual risks)
答案:登入後查看
統計: A(0), B(0), C(1), D(0), E(0) #2136036