195.According to the contract, what is the payment schedule for the Contractor?
(A)20% upfront, 50% upon completion of each milestone, remaining balance after final deliverables approval.
(B)20% upfront, 25% upon completion of each milestone, remaining balance after final deliverables approval.
(C)20% upfront, 25% upon signing the contract, remaining balance after final deliverables approval.
(D)20% upfront, 25% upon completion of each milestone, remaining balance due within 7 days of signing the contract.

答案:登入後查看
統計: A(4), B(69), C(14), D(83), E(0) #3171594

詳解 (共 2 筆)

#5971019
根據合同,承包商的付款時間表是怎樣的?(...
(共 238 字,隱藏中)
前往觀看
9
0
#6404273
題目詢問合約 找到合約處   Outs...
(共 1077 字,隱藏中)
前往觀看
4
0