四、On July 1, 2019, Torvill Construction Company Inc. contracted to build an office building for Gumbel
Corp. for a total contract price of $1,900,000. On July 1, Torvill estimated that it would take between 2 and 3
years to complete the building. On December 31, 2021, the building was deemed substantially completed.
Following are accumulated contract costs incurred, estimated costs to complete the contract, and
accumulated billings to Gumbel for 2019, 2020, and 2021.
At 12/31/19 At 12/31/20 At 12/31/21
Contract costs incurred to date $ 300,000 $1,200,000 $2,100,000
Estimated costs to complete contract 1,200,000 800,000 -0-
Billings to Gumbel 300,000 1,100,000 1,850,000
Instructions (12%)
Using the percentage-of-completion method, compute the profit or loss to be recognized as a result of this
contract for the years ended December 31, 2019, 2020, and 2021. (Ignore income taxes.)