17 甲公司自建廠房支出如下:鋼筋水泥等原物料支出$150,000,直接人工$500,000,分攤的間接成本$60,000,建築師廠房設計費$50,000,與興建廠房有關之專案借款$800,000,其專案借款成本為$20,000,設算之利息成本為$30,000。試問該自建廠房之成本為何?
(A)$810,000
(B)$780,000
(C)$760,000
(D)$710,000