25. When you are asked to ensure the preparations for entering the pilot station, which one of the following options is not the suitable answer?
(A) The stand-by air compressor has been already started and two sets of compressors are operating in parallel to fill up the air bottles.
(B) The starting system is now opened and other equipment for stand-by has been prepared.
(C) Three generators are operating in parallel.
(D) The turbocharger has been setup already and the safety valve of steam drum has been operating as open state.

正確答案:登入後查看

詳解 (共 1 筆)

推薦的詳解#6632346
未解鎖
(D)   理由:進入引水站前的待命準...