49.控制時程(control schedule)、報告績效(report performance)及管理採購(administer procurement)屬於哪個過程群組 (process group)的主要輸出?
(A)啟始(Initiating)
(B)規劃(Planning)
(C)執行(Executing)
(D)監控(Monitoring and Control)

答案:登入後查看
統計: A(3), B(10), C(20), D(60), E(0) #1881944