330 專案經理需律定專案發工的程序及誰有權核准發工,稱之:
(A)成本概估
(B)核准權限
(C)界定初使風險
(D)時程里程碑
答案:登入後查看
統計: A(0), B(163), C(3), D(6), E(0) #1612106