937 BAC(完工整預算)和 EAC(估計完工成本)比較的結果,稱為?
(A)完工變異(Variance at Completion, VAC)
(B)時程變異(Schedule Variance, SV)
(C)成本變異(Cost Variance, CV)
(D)趨勢分析(Trend Analysis)

答案:登入後查看
統計: A(103), B(11), C(29), D(2), E(0) #1612713

詳解 (共 1 筆)

#2361193
VAC完工變異=BAC完工整預算-EAC...
(共 65 字,隱藏中)