25. 就一般之生產規劃程序而論,產能需求規劃(capacity requirements planning, CRP)、物料需求規劃(MRP)及主生產排程(master production schedule, MPS)此三者之規劃先後次序應為
(A) CRP→MRP→MPS
(B) MRP→MPS→CRP
(C) MPS→MRP→CRP
(D) MRP→CRP→MPS
答案:登入後查看
統計: A(2), B(0), C(8), D(1), E(0) #2153514